Technical Quotation: sUAS Aerial Imagery of Levee Infrastructure
1. Summary of Our Quotation
The Government requires georeferenced aerial imagery and visual observations for 12 levee segments, about 38 miles in total, to support its annual inspection program. Deliverables must meet a ground sample distance (GSD) of 2 cm or better and arrive within 45 calendar days of award.
Skyline Survey LLC will:
- Fly all 12 segments within 21 days of award, weather permitting, leaving more than three weeks for processing, quality checks and delivery.
- Deliver orthomosaics at 1.5 cm GSD, better than the 2 cm required.
- Use FAA Part 107–certified remote pilots with visual observers on every flight.
- Provide an observation log flagging visible erosion, seepage indicators, encroachments and vegetation issues, each tied to coordinates and photos.
- Operate only aircraft that comply with the RFQ's restrictions on covered foreign-made unmanned aircraft (RFQ Section C.7).
2. Technical Approach
2.1 Flight planning
Each segment is planned in advance as a mapping mission with 75% forward and 70% side overlap at an altitude chosen to achieve 1.5 cm GSD. Before each mission, the pilot in command checks weather, NOTAMs and temporary flight restrictions. Where a segment lies in controlled airspace, we obtain FAA authorization through LAANC or a waiver before flying.
2.2 Ground control and accuracy
RTK-equipped aircraft and surveyed ground control points (at least five per segment) bring horizontal accuracy within 5 cm. Independent checkpoints, not used in processing, confirm accuracy, and the results are reported in the accuracy report (Deliverable 4).
2.3 Imagery and observations
Along with nadir mapping imagery, crews capture oblique photos of the levee crown, both slopes, toe and every structure listed in Attachment J-2 (culverts, gates and pump stations). Field observations are recorded on tablets with GPS location and photo links, then reviewed by the project manager before delivery.
2.4 Deliverables
| # | Deliverable (RFQ C.5) | Format | Due |
|---|---|---|---|
| 1 | Orthomosaic for each segment | GeoTIFF, project coordinate system | Day 40 |
| 2 | Oblique photo set with locations | JPEG plus index shapefile | Day 40 |
| 3 | Observation log | Spreadsheet and shapefile | Day 40 |
| 4 | Accuracy report | Day 40 | |
| 5 | Final summary report | Day 45 |
3. Safety Plan
- Written preflight and postflight checklists for every mission
- A visual observer on every flight; no flights over people or moving vehicles except as Part 107 allows
- Site-specific hazard briefing (power lines, levee traffic, wildlife) before each day's flying
- Flights stop for winds above the aircraft's limits, precipitation or reduced visibility
- Any incident or accident reported to the Contracting Officer's Representative within 24 hours, and to the FAA where required
4. Data Management and Security
Imagery is stored encrypted on company equipment, backed up daily and kept separate from other clients' data. Data is delivered by the Government's chosen secure method and deleted from our systems 90 days after acceptance unless the Government directs otherwise. We do not publish or share Government imagery.
5. Management and Schedule
A single project manager is the Government's point of contact and sends a short written status update every week.
| Days after award | Milestone |
|---|---|
| 1–5 | Kickoff call; access and coordination plan confirmed |
| 6–21 | Field data collection on all 12 segments |
| 22–38 | Processing, quality checks and observation review |
| 40 | Deliverables 1–4 submitted |
| 45 | Final summary report submitted |
6. Past Performance
| Customer | Work | Period | Value |
|---|---|---|---|
| Central Plains Water District | Drone mapping of 22 miles of canal and embankment | 2025 | $48,000 |
| Marion County Engineering | Bridge and culvert visual inspection imagery, 31 structures | 2024–2025 | $36,500 |
| Prairie Rail Partners | Corridor imagery and encroachment mapping, 15 miles | 2024 | $27,000 |
7. Compliance with Instructions (RFQ Section L)
| Instruction | Where addressed |
|---|---|
| L.2(a) Technical approach | Section 2 |
| L.2(b) Safety plan | Section 3 |
| L.2(c) Management and schedule | Section 5 |
| L.2(d) Past performance, up to three projects | Section 6 |
| L.3 Price in a separate volume | Volume II |
| L.4 SAM registration and UEI | Cover page of Volume II |